Pokarna Story
Metecno – Media – Case Study -Pokarna Story
Project : DRDO – Bengaluru
Scope: 5,500 sqm Rockwool panels, G+6 structure
Timeline : 7 5 Days
Pokarna Story - Chapter 1
A Challenge established
- 2019: Strategic decision to install a new discontinuous assembly line for Clean Room panels & precision products.
- Sudden requirement: M-Profile panels for granite slab production facility.
- Technical complexities emerged with the new line, requiring creativity, problem-solving, and teamwork.
- Turned into a defining moment for innovation and process improvement.

Pokarna Story - Chapter 2
Hurdles are aplenty
- Unique challenge: Factory design needed to comply with Vastu Shastra (first time for Metecno).
- Covid-19 impact (2020): Pandemic disrupted operations.
- Team lacked prior experience with M-Profile panels, making it a steep learning curve.
- Approach: Viewed challenges as opportunities to innovate and collaborate across disciplines.
- Outcome: Developed solutions ensuring technical success and client satisfaction.

Pokarna Story - Chapter 3
Determination is the Key
- Team fully committed to client’s requirements despite hurdles.
- Gradual clarity achieved in integrating Vastu principles into design.
- Careful verification of details avoided potential delays.
- Challenges faced:
- Delays in powder coating.
- Variations in panel widths.
- Procurement of glass & doors.
- Ensured timely dispatch of panels and accessories to the site.
- Covid impact + reduced timeframe led to ~1-month delay.
- Despite client frustration, maintained positive working relationship through diligent effort.

On a sultry evening of April, we were reviewing our sales plan at our H.O…..
Project : DRDO – Bengaluru
Time Period: 45 Days
It was a sweltering afternoon in the summer of 2021…..
Project : Adani Mundra
Time Period: – Days